Our Pool Engineers have create this process to explain our customer the process that is done when you hire P & H Pools in Miami or Broward County.
LAYOUT:
1- Pool Layout
We will stake out swimming pool according to the approved plans and confirm that access is ready for excavation.
EXCAVATION:
2 – Excavation
Heavy equipment arrives at jobsite to carry out excavation. Usually a 1-2 day process to complete.
STEEL REBAR:
3 – Steel Rebar
Installation of formwork and reinforcing steel rebar. Inspection required once formwork is completed.
SHOTCRETE:
4- Shotcrete
The most interesting step in the process! A special mix of concrete together with a high pressure compressor applies concrete to entire structure. This completes the pool structure phase.
PLUMBING:
5 – Plumbing
All pool plumbing is installed according to plans and pressure tested to insure no leaky pipes. Inspections are required once plumbing is completed.
COPING / TILE:
6- Coping and Tile
The coping / tile you selected are installed and leveled. At this step you will begin to see your pool come to life.
ELECTRICAL:
Our electrician will run all electrical conduits, cables and control boxes needed to power pool equipment. Inspections required once electrical is completed.
DECK:
7- Deck
The deck material you selected is installed.
INTERIOR FINISH:
This is the final step before your pool is completed. Our professional team of applicators will hand trowel the material of your choice to complete your pool.
START UP:
Finished-Pool
Once the pool is filled with water we will add initial chemical treatment and explain how to properly operate / maintain new pool.
PARTY TIME:
We are finished! Time to plan as many parties and events as you can tolerate. Enjoy!